Order For Custom Writing, Similar Answers & Assignment Help Services

Fill the order form details in 3 easy steps - paper's instructions guide.

Posted: June 29th, 2022

Earned Value Management Explained

Earned Value Management Explained

Earned Value Management (EVM) helps project ( help with nursing paper writing from experts with MSN & DNP degrees) managers to measure project ( help with nursing paper writing from experts with MSN & DNP degrees) performance. It is a systematic project ( help with nursing paper writing from experts with MSN & DNP degrees) management process used to find variances in project ( help with nursing paper writing from experts with MSN & DNP degrees)s based on the comparison of worked performed and work planned. EVM is used on the cost and schedule control and can be very useful in project ( help with nursing paper writing from experts with MSN & DNP degrees) forecasting. The project ( help with nursing paper writing from experts with MSN & DNP degrees) baseline is an essential component of EVM and serves as a reference point for all EVM related activities. EVM provides quantitative data for project ( help with nursing paper writing from experts with MSN & DNP degrees) decision making.

A baseline in project ( help with nursing paper writing from experts with MSN & DNP degrees) management is a clearly defined starting point for your project ( help with nursing paper writing from experts with MSN & DNP degrees) plan. It is a fixed reference point to measure and compare your project ( help with nursing paper writing from experts with MSN & DNP degrees)’s progress against. This allows you to assess the performance of your project ( help with nursing paper writing from experts with MSN & DNP degrees) over time.

For example, let’s say your project ( help with nursing paper writing from experts with MSN & DNP degrees) is on target to finish in six weeks. Is that good or bad? If your schedule baseline has a four-week completion, you can tell that there is a problem, and your team may need to make adjustments to speed up your progress. A project ( help with nursing paper writing from experts with MSN & DNP degrees) baseline typically has three components: schedule, cost, and scope

Common abbreviations

EV = earned value
AC = actual cost
PV = Planned value
BAC= Budget at Completion
VAC = Variance at Completion
EAC= Estimate at Completion
ETC = Estimate to complete

EVM Measures

EVM consists of the following primary and derived data elements. Each data point value is based on the time or date an EVM measure is performed on the project ( help with nursing paper writing from experts with MSN & DNP degrees).

Primary Data Points
• Budget At Completion (BAC)
Total cost of the project ( help with nursing paper writing from experts with MSN & DNP degrees)

• Budgeted Cost for Work Scheduled (BCWS) / Planned Value (PV)
The amount expressed in Pounds (or hours) of work to be performed as per the schedule plan
PV = BAC * % of planned work.

• Budgeted Cost for Work Performed (BCWP) / Earned Value (EV)
The amount expressed in Pounds (or hours) on the actual worked performed
EV = BAC * % of Actual work

• Actual Cost of Work Performed (ACWP) / Actual Cost (AC)
The sum of all costs (in Pounds) actually accrued for a task to date

Cost Forecasting:
• Estimate At Completion (EAC)
The expected TOTAL cost required to finish complete work
EAC = BAC / CPI
o = AC + ETC

• Estimate to complete (ETC)
The expected cost required to finish all the REMAINING work: below ETC is made the subject of the formula to find EAC above
ETC = EAC – AC

Reminder
EV = earned value
AC = actual cost
PV = Planned value
BAC= Budget at Completion
VAC = Variance at Completion
EAC= Estimate at Completion)
ETC = Estimate to complete

Variances:
• Cost Variances (CV)
How much under or over budget
CV = EV-AC
NEGATIVE is over budget, POSITIVE is under budget

• Schedule Variances (SV)
How much ahead or behind schedule
SV = EV-PV
NEGATIVE is behind schedule, POSITIVE is ahead of schedule

• Variance At Completion (VAC)
Variance of TOTAL cost of the work and expected cost
VAC = BAC – EAC

Performance Indices:
• Cost Performance Index
CPI = EV / AC
Over (< 1) or under (> 1) budget

• Schedule Performance Index
SPI = EV / PV
Ahead (> 1) or behind (< 1) schedule

To Complete Performance Index (TCPI) is a forecasting technique of Project Management (PM). It is the cost efficiency required to complete a project ( help with nursing paper writing from experts with MSN & DNP degrees) within a defined budget.
TCPI = [BAC-EV]
[EAC-AC]

TCPI Definitions
It is a measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget. (PMBOK Guide)

Difference Between CPI And TCPI

Both CPI and TCPI provide a measure of Project’s cost efficiency. However there are basic differences between these two figures.
Cost Performance Index (CPI) is defined as ratio of EV and AC (EV / AC). It is project ( help with nursing paper writing from experts with MSN & DNP degrees)’s current cost efficiency on the Control Date.

The project ( help with nursing paper writing from experts with MSN & DNP degrees) CPI could be any one of the following:
• CPI < 1 – it means that value earned value is less than the money spent. Project is over budget.
• CPI = 1 – it means that value earned value is equal to the money spent. Project is going as per the budget.
• CPI > 1 – it means that value earned value is more than the money spent. Project is under budget.

CPI is a measure of current cost efficiency of the project ( help with nursing paper writing from experts with MSN & DNP degrees). If CPI ≥ 1, then the project ( help with nursing paper writing from experts with MSN & DNP degrees) is (most probably) doing well. On the other hand, if CPI < 1 then the project ( help with nursing paper writing from experts with MSN & DNP degrees) is likely to be in trouble. In the latter case, the project ( help with nursing paper writing from experts with MSN & DNP degrees) team needs to take a corrective action(s) to bring the future costs in-line with the budget. This can be done by increasing the future cost efficiency.

As discussed earlier, TCPI is the estimated future cost efficiency.
CPI = (monetary value of completed work)/(expenditure till control date)
TCPI = (monetary value of remaining work)/(remaining funds)

The main differences between CPI & TCPI….

• CPI represents project ( help with nursing paper writing from experts with MSN & DNP degrees)’s current cost efficiency, whereas TCPI estimates project ( help with nursing paper writing from experts with MSN & DNP degrees)’s future cost efficiency.
• CPI is actual efficiency of the completed project ( help with nursing paper writing from experts with MSN & DNP degrees) work, whereas TCPI is estimated forecast of efficiency of the remaining project ( help with nursing paper writing from experts with MSN & DNP degrees) work.

A. You are managing a software project ( help with nursing paper writing from experts with MSN & DNP degrees) with an initial budget estimate of 2 million dollars. During your interim cost and schedule performance analysis, you figured out that:

 You should have spent $500,000 based on your initial plans and 1,000 man/days of schedule activities

 You spent $600,000 and completed 1,100 man/days of schedule activities which should have cost $450,000 based on your initial plans.

 You re-estimated the budget for the remaining work to be done as $1,500,000.

Calculate the following:
• BAC (Budget at Completion) = 2 million dollars
• PV (Planned Value) = $500,000 for cost related EVM calculations, PV=1,000 man/days for schedule related EVM calculations
• AC (Actual Cost) = $600,000
• EV (Earned Value) = 1,100 man/days for schedule related EVM calculations, EV = $450,000 for cost related EVM calculations.
• ETC (Estimate to Complete) = $1.5 million dollars

a. What is the Cost performance index (CPI ) and schedule performance index (SPI) of the project ( help with nursing paper writing from experts with MSN & DNP degrees) respectively?

• CPI = EV/AC = $450,000/$600,000 = 0.75
• SPI = EV/PV = 1,100/1,000 = 1.10
(4 marks)
b. What is the Cost variance (CV) and schedule variance ( SV) of the project ( help with nursing paper writing from experts with MSN & DNP degrees) respectively?
• CV = EV – AC = $450,000 – $600,000 = -$150,000
• SV = EV – PV = 1,100 man/days – 1,000 man/days = 100 man/days
(4 marks)
c. What is the Variance at Completion?
VAC (Variance at Completion) = BAC – EAC
= 2 million dollars – EAC

We know that EAC (Estimate at Completion) = AC + ETC
= $600,000 + $1,500,000
= $2,100,000

Therefore VAC = $2,000,000 – $2,100,000 = -$100,000
(4 marks)
d. What is the TCPI based on your new Estimate at Completion value?
TCPI based on EAC is calculated as below:
TCPI = [BAC-EV] / [EAC-AC]
= [$2,000,000-$450,000] / [$2,100,000-$600,000]
TCPI (based on EAC) = 1.03
(2 marks)
e. What is the status of your project ( help with nursing paper writing from experts with MSN & DNP degrees)?
Project is ahead of schedule, over budget, and it is harder to complete the project ( help with nursing paper writing from experts with MSN & DNP degrees) on new EAC
(2 marks)
We can calculate
CPI = EV / AC = 450,000 / 600000 =
Over (< 1) or under (> 1) budget

Students’ Problem:
Eg. A Company has initial budget estimate of 3 million dollars. During your interim cost and schedule performance analysis, it was realized:

 You should have spent $600,000 based on your initial plans and 2,000 man/days of schedule activities

 You spent $700,000 and completed 2,100 man/days of schedule activities which should have cost $550,000 based on your initial plans.

 You re-estimated the budget for the remaining work to be done as $2,500,000.

Therefore:
• BAC (Budget at Completion) = 3 million dollars
• PV (Planned Value) = $600,000 for cost related EVM calculations, at PV=2,000 man/days for schedule related EVM calculations
• AC (Actual Cost) = $700,000
• EV (Earned Value) = 2,100 man/days for schedule related EVM calculations, EV = $550,000 for cost related EVM calculations.
ETC (Estimate to Complete) = $2.5 million dollars

Find the following:
a. What is the CPI and SPI of the project ( help with nursing paper writing from experts with MSN & DNP degrees) respectively?
f. What is the CV and SV of the project ( help with nursing paper writing from experts with MSN & DNP degrees) respectively?
g. What is the Variance at Completion?
h. What is the TCPI based on your new Estimate at Completion value?
i. What is the status of your project ( help with nursing paper writing from experts with MSN & DNP degrees)?

Reference
Dwivedi U., (2015). Earned Value Management Explained. Retrieved from
https://www.project ( help with nursing paper writing from experts with MSN & DNP degrees)smart.co.uk/earned-value-management-explained.php

Malik P., (2020). How To Use To Complete Performance Index (TCPI) Formulas In PMP? Retrieved from https://www.pmbypm.com/tcpi-to-complete-performance-index/

Order | Check Discount

Tags: apps that write essays for you free, assignment writing services in usa, bes, best dissertation writing services, best essay writing service

Assignment Help For You!

Special Offer! Get 15-30% Off on Each Order!

Why Seek Our Custom Writing Services

Every Student Wants Quality and That’s What We Deliver

Graduate Essay Writers

Only the most qualified writers are selected to be a part of our research and editorial team, with each possessing specialized knowledge in specific subjects and a background in academic writing.

Affordable Prices

Our prices strike the perfect balance between affordability and quality. We offer student-friendly rates that are competitive within the industry, without compromising on our high writing service standards.

100% Plagiarism-Free

No AI/chatgpt use. We write all our papers from scratch thus 0% similarity index. We scan every final draft before submitting it to a customer.

How it works

When you decide to place an order with Nursing.StudyBay, here is what happens:

Fill the Order Form

You will complete our order form, filling in all of the fields and giving us as much guidelines - instruction details as possible.

Assignment of Writer

We assess your order and pair it with a skilled writer who possesses the specific qualifications for that subject. They then start the research/writing from scratch.

Order in Progress and Delivery

You and the assigned expert writer have direct communication throughout the process. Upon receiving the final draft, you can either approve it or request revisions.

Giving us Feedback (and other options)

We seek to understand your experience. You can also review testimonials from other clients, from where you can select your preferred professional writer to assist with your homework assignments.

Expert paper writers are just a few clicks away

Place an order in 3 easy steps. Takes less than 5 mins.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00